KUALA LUMPUR: The commissioning of Malaysia’s first two littoral combat ships (LCS) has been delayed, defence minister Khaled Nordin said today. Speaking in the Dewan Rakyat, Khaled said the ...
Free Malaysia Today on MSN
Not true, minister says on A-G’s 2035 projection for LCS 1
Khaled Nordin says alternative missile deals Malaysia is seeking with other nations will only take three years for delivery ...
The LCS project was 7.55% behind schedule across all five ships, while LCS 1 was 13.88%, or 108 days, behind in equipment, construction, trial and commissioning work. The navy’s first littoral combat ...